Environmental Clearance Categories Under the 2023 Rules

The Environment Conservation Rules 2023 sort every project into four environmental clearance categories, and that label decides the paperwork, the timetable and sometimes whether a Sylhet site can be used at all. This note explains the Green, Yellow, Orange and Red routes and the local factors that change them.

Factory site in Sylhet assessed under the environmental clearance categories of the 2023 Rules

Key takeaways

  • The 2023 Rules create four environmental clearance categories: Green, Yellow, Orange and Red.
  • Green projects apply directly for environmental clearance; the other three need a site clearance first.
  • Red projects need an EIA by a listed consultant and a public consultation.
  • No construction, utility connection or trial production before the required clearance.
  • Operating without clearance can mean two to five years' imprisonment or fines up to Tk 5 lakh.

How the environmental clearance categories work

Under the Environment Conservation Rules 2023, every industrial unit or project is placed in one of four environmental clearance categories — Green, Yellow, Orange or Red — and the category decides which certificates you need from the Department of Environment (DoE), what you must file and how long the DoE has to decide. Green projects apply straight for an environmental clearance certificate. Yellow, Orange and Red projects must first obtain a site clearance (locational clearance) and only then an environmental clearance. The Rules were published in the Bangladesh Gazette on 5 March 2023 as SRO No. 53 and replaced the 1997 Rules.

Factory site in Sylhet assessed under the environmental clearance categories of the 2023 Rules
The environmental clearance categories decide whether a Sylhet project needs a site clearance, an IEE or a full EIA before it can be built.

The legal basis is section 12 of the Bangladesh Environment Conservation Act 1995, which prohibits establishing an industrial unit or undertaking a project without an environmental clearance from the Director General of the DoE. The 2023 Rules supply the machinery: rule 5 creates the four environmental clearance categories, Schedule 1 lists which activities fall into each, and Schedule 14 is used to classify an activity that does not appear in Schedule 1. For anyone planning a factory, a resort, a brick kiln, a crusher or a filling station in the Sylhet division, the first practical question is therefore not "how do I apply?" but "which category am I in?"

The Rules define each category by its likely impact. Green covers units with comparatively very low impact on the environment and human health. Yellow covers moderate impact that needs mitigation. Orange covers significant impact that must be reduced through appropriate pollution control. Red covers severe impact requiring substantial mitigation. The descriptions are general; the binding answer is the activity's entry in Schedule 1.

The four environmental clearance categories at a glance

The table below summarises the route for each of the environmental clearance categories as set out in rules 6 and 9 to 16 of the 2023 Rules. The time limits are counted in working days from a complete application, and they bind the DoE office rather than guarantee an outcome.

CategorySite clearance first?Main documentsDecision time in the Rules
GreenNo — apply directly for environmental clearance (rule 6 proviso, rule 9)Form 3, supporting papers, fee under Schedule 7Environmental clearance within 7 working days after site inspection, or written refusal with reasons
YellowYes (rule 10), then environmental clearance (rule 11)Form 3, processing fee under Schedule 6, documents, Schedule 9 guidanceApplicant told to pay the clearance fee within 8 working days; site clearance within 7 working days of payment; refusal notified within 15 working days; environmental clearance within 7 working days of the second application
OrangeYes (rule 12), then environmental clearance (rule 13)Form 3, fee, initial environmental examination (IEE) reportSite clearance within 21 working days; environmental clearance within 20 working days; refusal reasons within 5 working days of the decision
RedYes (rule 14), with terms of reference for an EIAForm 3, fee, draft EIA terms of reference, then EIA and environmental management planTerms of reference approved within 30 working days; EIA by a listed consultant; public consultation before environmental clearance

Two exemptions matter in practice. Under rule 6, units inside a government or private export processing zone, an economic zone or an industrial estate of the Bangladesh Small and Cottage Industries Corporation (BSCIC) do not need a separate site clearance — only the environmental clearance. Investors looking at an economic zone or hi-tech park in the division should still check the zone authority's own rules, which sit alongside the DoE regime; our page on economic zones and hi-tech parks explains them.

Green and Yellow: the lighter environmental clearance categories

For a Green unit the process is a single step. The proponent files Form 3 with the documents and fee, the DoE office inspects the site, and within seven working days of that inspection it either grants the environmental clearance or refuses it in writing with reasons (rule 9). Typical Green activities are light assembly and service businesses; check Schedule 1 rather than assuming.

A Yellow unit goes through two stages. First comes the site clearance: the office examines the application, inspects the site within eight working days and asks for the fee; once the fee is paid, the site clearance should follow within seven working days, and a rejection must be notified within fifteen working days (rule 10). With the site clearance in hand the proponent builds, installs the agreed pollution controls and then applies for the environmental clearance itself, which the office must decide within seven working days of a complete application (rule 11).

  1. Confirm the Schedule 1 entry and the correct DoE office (district office, divisional office or head office, depending on how many districts the project spans — rule 7).
  2. File online. Rule 7 requires online filing, with paper filing allowed only if the online system cannot be used.
  3. Keep the inspection report and fee receipt; they evidence the date from which the DoE's time limit runs.
  4. Do not order gas, power or water connections before the site clearance — utilities may not connect Yellow, Orange or Red units without it (rule 6(3)).

Orange and Red: committees, IEE and EIA

Orange and Red are where most of the cost and delay sits, and where the environmental clearance categories most often decide whether a project is viable at a given site. An Orange application must include an initial environmental examination (IEE). The district or divisional office inspects the site, prepares a report on the reasonableness of granting a site clearance and sends it to an environmental clearance committee. Schedule 1 splits the Orange list: serial numbers 1 to 62 go to the regional, divisional or metropolitan committee, while serial numbers 63 to 113 go to the committee at DoE head office (rules 12 and 13).

Where the head office committee finds, on reviewing the IEE, that an Orange project could seriously affect the environment and human health, it may recommend a full environmental impact assessment (EIA), and with the Director General's approval the proponent must then carry one out (rule 13(6)). Budget for that possibility when a project sits near the top of the Orange list.

Red projects begin with draft terms of reference for an EIA, prepared using the Schedule 10 guidance. The head office committee approves those terms within thirty working days. The EIA itself must be prepared by a consultant on the DoE's list (rule 15), and the proponent must make a written declaration (Form 6) that it will implement the environmental management plan.

Rule 16 adds a public consultation stage for Red projects. The proponent publishes a notice in one local and one national daily, a Bangla summary of the EIA is filed, the DoE posts details on its website, and comments may be made for thirty working days. The hearing should normally take place within forty-five working days of the draft EIA, with a further fifteen working days allowed where necessary, and the minutes of the hearing are attached to the final EIA.

Practical point

Choose your site before you choose your consultant. In the Sylhet division, a site inside or close to an ecologically critical area, a hill or a mapped wetland can turn an otherwise ordinary Orange project into one the DoE cannot approve at all, whatever the quality of the IEE or EIA.

What you cannot do before clearance

Rule 6 contains the restrictions that most often catch Sylhet developers out:

  • No land development or construction of any infrastructure for a Yellow, Orange or Red unit before the site clearance (rule 6(2)).
  • No gas, electricity, water or other utility connection for such a unit before the site clearance (rule 6(3)).
  • No trial production or project operation in any category before the environmental clearance (rule 6(4)).

Breaching section 12 of the 1995 Act — operating without an environmental clearance — carries imprisonment of two to five years or a fine of Tk 1 lakh to Tk 5 lakh, or both, under item 12 of the penalty table in section 15. The DoE can also issue directions under section 7 to pay compensation or take remedial measures, and a lender, buyer or insurer will usually ask for the clearance as a condition. Our page on environmental clearance in Sylhet covers renewals, conditions and enforcement in more detail.

Illustration (hypothetical): a family in Birmingham funds a cousin's rice-milling and drying unit near Beanibazar. Local contractors raise the boundary wall and pour the shed floor before anyone checks the category. If the activity sits in a category that needs a site clearance, that early construction is itself a breach of rule 6(2), and the DoE may refuse the site clearance or attach conditions that require the layout to be changed. Classifying the project before buying cement would have cost nothing.

Sylhet factors that change the analysis

The environmental clearance categories describe the activity, but the Sylhet landscape often decides the answer. Several statutory restrictions apply regardless of category:

FeatureLegal restrictionEffect on a clearance
Ecologically critical area (for example the Jaflong–Dawki river area)Activities listed in the section 5 notification are prohibitedDoE cannot clear a prohibited activity inside the area
Hills and tilas (hillocks)Section 6B bars cutting or razing hills, save for essential national interest with DoE clearanceHillside sites need specific DoE permission for any cutting
Water bodies marked as reservoirsSection 6E bars filling or changing their class, save for essential national interest with DoE clearanceHaor-edge or beel-side land may be unusable for building
Brick kilnsEnvironmental clearance is a precondition of the Deputy Commissioner's kiln licenceSiting rules under the 2013 Act are checked as well

See our notes on hill cutting offences and permissions and on ecologically critical areas around Sylhet before committing to a site, and the energy, natural resources and environment overview for the wider regime.

Refusals, conditions and appeals

A clearance is usually granted with conditions — effluent treatment, emission limits, monitoring and reporting — and breaching a condition can lead to suspension or cancellation. If the DoE refuses, the Rules require written reasons. Section 14 of the 1995 Act allows a person aggrieved by a notice, order or direction to appeal to the appellate authority within thirty days, extendable by up to a further thirty days for sufficient cause; the authority's decision is stated to be final, although constitutional review by the High Court Division remains available in an appropriate case. Because the environmental clearance categories are fixed by Schedule 1, a challenge to classification is usually better argued on the facts of the activity than on general fairness.

How TRW & Co helps

We advise project owners, investors and landowners on which of the environmental clearance categories applies, prepare and check DoE applications, coordinate with IEE and EIA consultants, and review site-specific constraints such as ECAs, hills, wetlands and khas land before money is committed. We also act in appeals against refusals and in enforcement proceedings. Clients in the UK and elsewhere can instruct us by email at info@trw.co, and papers can be reviewed remotely; meetings take place at our Sylhet office at Surma Tower, opposite the Judge Court. To discuss a project, please contact us.

Frequently asked questions

Which of the environmental clearance categories applies to my project?

Schedule 1 to the Environment Conservation Rules 2023 lists activities under Green, Yellow, Orange and Red. If your activity is not listed, rule 5 says it is classified using Schedule 14. Check the exact activity description, capacity and inputs, because similar businesses can fall into different categories depending on scale and process.

Do I need a site clearance in an economic zone?

Rule 6 says units in government or private export processing zones, economic zones and BSCIC industrial estates do not need a site clearance and apply only for the environmental clearance. The zone authority's own approvals still apply, so check both regimes before signing a lease.

How long does the DoE take to decide?

The Rules set working-day limits: for example seven working days after inspection for Green, twenty-one working days for an Orange site clearance and thirty working days to approve Red EIA terms of reference. These limits run from a complete application and do not guarantee approval; incomplete files restart the clock in practice.

Can I start building while my application is pending?

Not for Yellow, Orange or Red units. Rule 6 bars land development and infrastructure before the site clearance, bars utility connections, and bars trial production before the environmental clearance. Early works can lead to refusal, conditions or penalties under the 1995 Act.

What if the DoE refuses my application?

The DoE must give written reasons. Section 14 of the Environment Conservation Act 1995 allows an appeal to the appellate authority within thirty days, with up to thirty more days for sufficient cause. In appropriate cases a writ petition in the High Court Division may also be considered.

Sources

  1. Environment Conservation Rules 2023, Bangladesh Gazette Extraordinary, 5 March 2023 (SRO 53)
  2. Bangladesh Environment Conservation Act 1995 (bdlaws)
  3. Brick Manufacturing and Kiln Establishment (Control) Act 2013 (bdlaws)

General information only, not legal advice. References to statutes, courts and authorities describe published law and practice at the date shown.