Guide · Land, Property and Title in Sylhet
Apartments and Real Estate Development in Sylhet
Real estate development in Sylhet is regulated by the Real Estate Development and Management Act 2010 and the Power of Attorney Act 2012. This guide explains joint-venture agreements, development powers of attorney, buyer protections, approvals and the 2026 land use limits, and what to do when a project fails.
Key takeaways
- Developers must register and obtain project approval before advertising or selling flats.
- Joint-venture agreements must state the developer's share, timetable and power-of-attorney terms.
- Irrevocable development powers of attorney must be registered and have a fixed term.
- Late handover entitles buyers to a refund with compensation within six months.
- Selling a contracted flat to someone else carries up to three years' imprisonment.
How real estate development in Sylhet is regulated
Real estate development in Sylhet is governed mainly by the Real Estate Development and Management Act 2010, which applies to developers building flats or plots for sale, to landowners who sign joint-venture agreements with them, and even to individuals who build on their own land for sale.
Alongside it sit the Power of Attorney Act 2012 (which regulates the powers landowners give developers), the Registration Act 1908, building-control rules and the Bangladesh National Building Code, and the 2026 land use and haor statutes. For landowners the key document is the joint-venture agreement; for buyers it is the allotment letter and the registered deed of the flat with its share of land.

Sylhet city has seen rapid apartment construction, much of it funded by remittances and bought by families abroad who may never see the building until handover. That creates familiar risks: projects started without approval, flats sold twice, delayed handover, missing utilities and landowners left with unfinished buildings. The 2010 Act was designed to address exactly these problems, and it gives both landowners and buyers concrete rights and criminal sanctions to rely on.
Who the 2010 Act covers and who regulates
The Real Estate Development and Management Act 2010 (Act No. 48 of 2010) requires developers to register with the relevant authority before carrying on real estate business. Under section 4, the government may declare authorities for particular areas; the Act names city development authorities where they exist and, in their absence, the relevant city corporation for its area, as well as municipalities and cantonment boards for theirs. In practice, a developer working in Sylhet city deals with Sylhet City Corporation for approvals, subject to any government notification designating a different authority and to the planning role of the Sylhet Development Authority discussed below.
Section 7 extends the Act beyond professional developers, which surprises many families who think of themselves simply as building a home with a few extra flats. A developer who buys land and builds for sale on its own account is covered, and so is an individual or group of individuals who build on their own land for the purpose of sale, so far as the provisions apply. A family that builds a block in Zindabazar or Uposhohor and sells some flats to outsiders should therefore treat itself as subject to the Act.
| Developer obligation | Section | Penalty for breach (maximum) |
|---|---|---|
| Register before carrying on real estate business | 5, 19 | Two years' imprisonment or Tk 10 lakh fine, or both |
| Not start work, advertise or sell an unapproved project | 6, 20 | Two years' imprisonment or Tk 10 lakh fine, or both |
| Not cancel an allotment without 60 days' registered notice | 14, 22 | One year's imprisonment or Tk 5 lakh fine, or both |
| Not mortgage allotted units without consent | 16, 23 | One year's imprisonment or Tk 5 lakh fine, or both |
| Not sell a contracted unit to someone else | 24 | Three years' imprisonment or Tk 20 lakh fine, or both |
| Use promised materials and follow the approved plan | 25, 26 | Three years' imprisonment or Tk 20 lakh fine, or both |
| Not abandon the project without compensating landowner or buyer | 27 | Two years' imprisonment or Tk 20 lakh fine, or both |
Under section 35 the court may order up to half of any fine recovered from a convicted developer to be paid to the affected landowner or buyer.
The landowner–developer agreement
Most real estate development in Sylhet is done on a joint-venture basis: the landowner contributes the plot, the developer builds, and the flats are divided in agreed proportions. Section 10 of the 2010 Act requires a written bilateral agreement between landowner and developer. It must state the developer's share, include the term that the landowner will execute a power of attorney authorising the developer to sign and register deeds for that share in favour of the developer's nominated buyers, and specify when development or construction will start and finish.
What a landowner should insist on
- Clear title first. The developer will check title; so should you. Partition among co-heirs and mutation should be complete before signing.
- Precise division of flats. Identify the landowner's flats, floors, parking and common areas by number on a plan attached to the agreement.
- Specifications. Attach a schedule of materials and fittings; substitution with inferior materials is an offence under section 25.
- Approvals and timetable. Make the developer responsible for obtaining building approval, with start and completion dates and a defined grace period.
- Compensation for delay. Fix monthly compensation or rent for the landowner if completion is late.
- Signing money. Record any upfront payment and how it is treated.
- Termination. Set out what happens if the developer abandons the project, including return of the land and the power of attorney.
- Dispute resolution. Section 36 requires parties first to try to settle and then to go to arbitration under the Arbitration Act 2001; make sure the agreement works with that scheme.
The development power of attorney
The power of attorney that a landowner gives a developer is regulated by the Power of Attorney Act 2012. An irrevocable power of attorney for land development in return for consideration must have a fixed term (section 4(1)) and must be registered, with the section 52A particulars of the Registration Act (section 6).
Even after the term ends, the developer's power to sell or mortgage its own share continues until exercised (section 4(2)).
If the purpose of the power is frustrated or a party is harmed, either side may terminate it by thirty days' notice by registered post, with a copy to the sub-registry (section 4(3)); the power is then suspended until any dispute is resolved under section 13, which sets out a sequence of negotiation, a jointly appointed mediator and, failing that, court proceedings. The term can be extended only by a registered agreement (section 4(5)).
Never give a developer a power of attorney over your entire plot. The power should cover only the developer's agreed share of flats and the land attached to them, should be time-limited, and should be signed at the same time as, and expressly linked to, the registered joint-venture agreement.
Tax and costs on the landowner's side
A joint venture is a transaction with tax and registration consequences for the landowner as well as the developer. The transfer of the developer's share of land to buyers, the registration of the power of attorney and the eventual flat deeds all attract duties and fees, and income tax may arise on the landowner's side. These are set by statute and notifications that change from year to year, so the agreement should state clearly who bears each cost. Leaving this vague is a frequent source of dispute at handover, when the landowner discovers that registration of their own flats carries costs they had assumed the developer would pay.
Buying a flat: buyer protections in the Act
For buyers, real estate development in Sylhet is safest when the project is approved, the developer registered and the landowner's title clean. Section 6 requires a developer to show the buyer the authority's approval and the title documents to the land, to print its registration number and plan approval details in its prospectus, and not to advertise or sell before project approval and before obtaining the power to execute transfer deeds. Section 8 requires the allotment letter or prospectus to explain the saleable area and its breakdown, and bars the developer from charging more than the contract price, save for agreed upgrades.
- Payments through banks. Section 12 requires payments to be made through a bank, and bars interest other than on instalments until the unit is ready for handover with services connected.
- Cancellation. A developer may not cancel an allotment for non-payment without at least 60 days' notice by registered post, and must refund the buyer's deposits within three months of cancellation (section 14).
- Late handover. If the developer fails to hand over on time, it must refund all money paid with the agreed compensation within six months; where the contract fixes no rate, the Act provides a default rate of compensation on the money paid (section 15).
- Utilities and defects. Units must have utility connections such as water, electricity, sewerage and fire safety (where applicable) before handover, and the developer remains responsible for certain construction defects after handover (sections 11 and 13).
- Mortgages. A mortgaged unit may not be sold to a buyer, and the developer needs the buyer's consent to mortgage an allotted unit (section 16).
- Documents at handover. The buyer must receive copies of the approved architectural, structural and building-services drawings, countersigned by the developer, together with the possession handover letter.
The flat and its undivided share of land must then be transferred by a registered deed, and the land share should be mutated into the buyer's name. Our insight on buying flats in Sylhet city gives a checklist.
Approvals and land use for real estate development in Sylhet
Building approval in Sylhet city is obtained from the competent authority, at present generally Sylhet City Corporation within its area, under the building-control rules and the Bangladesh National Building Code. The Sylhet Development Authority Act 2023, brought into force by notification of 19 January 2026, now also gives the Sylhet Development Authority a statutory role in planning and development clearance in and around the city, so check which authority approves plans for your plot.
Outside the city, municipalities and other authorities have their own procedures. The 2010 Act forbids any change to an approved plan without the authority's approval, and building outside the approved plan is an offence under section 26. Projects of a certain size or type may also require environmental clearance from the Department of Environment; see environmental clearance.
Two 2026 statutes now constrain where real estate development in Sylhet can happen. The Land Use Control and Agricultural Land Protection Act 2026 restricts the use of multi-crop agricultural land for non-agricultural purposes, prohibits changing the recorded class of land without approval, and makes building commercial housing on agricultural land, water bodies or wetlands an offence.
The Bangladesh Haor and Wetland Conservation Act 2026 bars filling and conversion of haors and wetlands and requires the opinion of the Department of Haor and Wetland Development for development projects in those areas. Developers acquiring land on the edges of the city, where paddy fields and low-lying land are common, must check both.
When a project goes wrong
Disputes over real estate development in Sylhet usually involve delay, abandonment, defective construction, a flat sold twice or a dispute between the landowner and the developer over the division of units. Remedies depend on who is complaining and what the contract says.
| Problem | Typical remedies |
|---|---|
| Developer abandons the project | Terminate the power of attorney by notice; arbitration or suit for possession and damages; complaint under section 27 |
| Handover delayed | Refund with compensation under section 15, or a supplementary agreement extending time with compensation |
| Flat sold to someone else | Criminal complaint under section 24; civil suit for specific performance or damages |
| Inferior materials or deviations from plan | Complaint under sections 25 and 26; claims for rectification costs |
| Landowner and developer disagree on allocation | Negotiation, then arbitration under the Arbitration Act 2001 as section 36 requires |
Buyers may also have remedies under consumer protection law; see our insight on consumer complaints against developers.
Illustration: an unfinished block
Illustration (hypothetical): a landowner in Sylhet city signs a joint-venture agreement for a six-storey building. The developer completes the frame, sells several of its flats to buyers in the UK, then stops work for over a year.
The landowner's options include serving notice to terminate the development power of attorney under section 4(3) of the 2012 Act, which suspends it pending resolution; starting the negotiation and arbitration process required by section 36 of the 2010 Act; and considering a complaint under section 27 for abandonment. The buyers, for their part, can claim refunds with compensation under section 15.
A negotiated takeover by another developer, with all parties' rights recorded in registered documents, is often the most practical outcome. Whatever route is chosen, the landowner should secure the site, photograph the state of works, and gather the agreement, the power of attorney, the approvals and the list of buyers, since each will be needed whether the matter ends in settlement, arbitration or court.
Preventing disputes at the outset
Most failures in real estate development in Sylhet can be traced to the first month of the project: a vague agreement, a broad power of attorney, an unregistered developer or a plot with unresolved inheritance. Landowners and buyers who insist on clean title, registered documents, a clear timetable and payment through banks are far better placed if something later goes wrong. A short legal review at signing costs a fraction of an arbitration or a suit, and gives every party a record of what was promised.
How TRW & Co helps
We advise landowners, developers, buyers and lenders on real estate development in Sylhet. From our office at Surma Tower, opposite the Judge Court, we review title, draft and negotiate joint-venture agreements and development powers of attorney, check developer registration and building approvals, and register flat deeds and follow through with mutation. When projects fail, we act in arbitrations, civil suits and criminal complaints under the 2010 Act, and negotiate takeovers and settlements.
Many buyers are abroad; we review allotment letters and deeds for them and report by email at info@trw.co. Contact us before you sign.
Frequently asked questions
Does the 2010 Act apply if my family builds flats on our own land?
Yes, if you build for the purpose of sale. Section 7 applies the Act, so far as relevant, to individuals and groups who build on their own land for sale even if they are not professional developers. You should take advice on registration, approvals and the documents buyers will expect before selling flats.
What share of flats should a landowner get?
There is no legal formula; the split is negotiated and depends on location, plot size, permitted floor area and market conditions. What the law requires is that the developer's share be stated in the written agreement. Make sure the landowner's units are identified by number on an attached plan.
Can I cancel the power of attorney I gave my developer?
An irrevocable development power of attorney cannot simply be withdrawn during its term. But if its purpose is frustrated or a party suffers loss, either side may terminate it by thirty days' notice by registered post, with a copy to the sub-registry. It is then suspended until the dispute is resolved by negotiation, mediation or court proceedings.
The developer is two years late. What can I claim as a buyer?
Under section 15 of the 2010 Act, if the developer fails to hand over on time, it must refund all money paid with the compensation stated in the contract within six months, and the Act provides a default rate where the contract is silent. Alternatively, you can agree in writing to extend time with compensation.
How do I check a project from abroad?
Ask for the developer's registration certificate, the building approval and the landowner's title documents, which the developer must show under section 6. A lawyer in Sylhet can verify them with the authority, inspect the site and review the allotment letter before you pay. Pay only through banking channels.
Sources
General information only, not legal advice. References to statutes, courts and authorities describe published law and practice at the date shown.