Real Estate and Construction in Sylhet
Real estate and construction in Sylhet is shaped by remittance money, joint venture towers and family-built homes. This guide explains the Real Estate Development and Management Act 2010, the Sylhet Development Authority Act 2023, the 2026 building regulator and the contracts that protect landowners, buyers and diaspora investors.
Key takeaways
- Developers must register before doing business, and prospectuses must show plan approval numbers.
- After full payment, a developer must hand over and register the flat within three months.
- Late handover means refund with compensation, defaulting to 15% where the contract is silent.
- Joint venture agreements must be written and fix the developer’s share and timetable.
- The Sylhet Development Authority Act 2023 and the Building Regulatory Authority Act 2026 reshape planning control.
Real estate and construction in Sylhet at a glance
Real estate and construction in Sylhet is driven to an unusual degree by remittances. Apartment blocks in Sylhet city, shopping complexes in Zindabazar and Ambarkhana, family homes in the upazilas and commercial buildings in Moulvibazar and Habiganj are often financed by family members in the UK, Europe or the Gulf. Around them sits a supply chain of developers, contractors, engineers, brick and stone suppliers, and buyers who may never have seen the property in person. The legal framework is a mix of property law, the Real Estate Development and Management Act 2010, building control, planning and environmental rules, and ordinary contract law.

This sector page is written for the main participants: landowners who sign joint venture agreements with developers, developers and contractors, buyers of flats and commercial space, and diaspora families funding a build from abroad. It summarises the rules that matter most, flags the 2023 to 2026 changes to the planning and building regulatory landscape, and links to our detailed pages. For the land side, see apartments and real estate development.
Who regulates what
| Issue | Main law or body | Notes |
|---|---|---|
| Developer registration and developer-buyer and landowner-developer relations | Real Estate Development and Management Act 2010 (Act 48 of 2010) | Registration with the designated authority; mandatory terms; criminal penalties |
| Building plan approval in Sylhet city | Sylhet City Corporation, alongside the Sylhet Development Authority's statutory role (check which authority approves your plot); building construction law | Approval before construction; compliance with the national building code |
| Planning and development clearance in and around Sylhet city | Sylhet Development Authority Act 2023 (Act 48 of 2023) | Master plan, land-use control and clearance for development; check how far the authority is operational |
| National oversight of plan approval and code compliance | Bangladesh Building Regulatory Authority Act 2026 (Act 66 of 2026) | Supervisory authority over plan-approving bodies; building construction committees outside cities and municipalities |
| Environmental clearance | Environment Conservation Act 1995 and Rules 2023 | Larger projects and certain locations |
| Land title, registration and mutation | Registration Act 1908, land records system | See our land pages |
Developers and buyers under the 2010 Act
The 2010 Act requires every real estate developer to register with the relevant authority before doing business in an area (section 5). A developer's prospectus must show its registration number, name, address and the approval number and date of the approved plan (section 6). The prospectus or allotment letter must explain the saleable area, including how it is divided, and set out detailed terms of the sale (section 8). Buyers pay through a bank as set out in the prospectus or allotment letter (section 12), and the developer must take effective steps to connect water, electricity and gas, where applicable, before handover (section 13).
Key protections for buyers
- Handover and registration. After full payment, the developer must hand over possession and complete execution and registration of the deed within three months (section 9).
- Delay. If the developer fails to hand over within the agreed time, it must refund all money paid with the agreed compensation within six months by account-payee cheque; if the contract does not fix compensation, it is set at 15% of the money paid (section 15).
- Mortgages. A developer may not sell a flat it has mortgaged, except as the section permits with the buyer's consent (section 16).
- Cancellation by the buyer. A buyer who asks in writing to cancel an allotment is refunded after the developer deducts 10% for incidental costs, on the terms of section 17.
- Default by the buyer. The consequences of missed payments must be spelled out in the prospectus or allotment letter, and an allotment cannot be cancelled without the notice the Act requires (sections 14 and 22).
Offences
The Act creates a series of offences. Doing real estate business without registration, or starting a project or advertising or selling an unapproved project, carries up to two years' imprisonment or a fine of up to Tk 10 lakh, or both (sections 19 and 20). Building outside the approved plan carries up to three years or a fine of up to Tk 20 lakh, or both (section 26), as does selling a promised flat elsewhere without the buyer's knowledge (section 24). Offences are compoundable, bailable and non-cognisable (section 32), and are tried summarily by a first-class or metropolitan magistrate (section 33). Directors and officers with knowledge of and participation in an offence by a developer company can also be liable (section 31).
For buyers of commercial units, such as shops in a market complex, the same Act applies, but there are additional points to check: whether the unit can lawfully be used for the intended trade, how service charges and common areas will be managed, and whether the developer retains rights over rooftops, signage or parking that affect the value of the unit.
Our insight on buying flats in Sylhet city lists what to check in an allotment letter.
Landowners and developer joint ventures
In Sylhet city the common model is a joint venture: a landowner contributes land and the developer builds, with the flats divided in agreed proportions. Section 10 of the 2010 Act requires a written bilateral agreement that states the developer's share, provides for a power of attorney so the developer can sell its share to its nominated buyers, and sets the start and completion dates for the work, which must then be met.
The Act backs the agreement with offences on both sides. A landowner who fails to hand over possession within the agreed time, or who cancels the registered power of attorney given to the developer without at least thirty days' notice, faces up to two years' imprisonment or a fine of up to Tk 10 lakh, or both (sections 28 and 29). A developer who fails to complete properly and hand over the landowner's share on time is also exposed (section 30).
Many joint venture disputes in Sylhet involve landowners who are co-heirs, some living abroad. Every co-owner must sign the agreement and the power of attorney, and co-owners abroad need properly executed and authenticated powers of attorney. One missing signature can stall a project for years. See power of attorney from the UK and abroad.
Illustration: a hypothetical Sylhet family of six siblings, three in Birmingham, signs a joint venture for a ten-storey building on their late father's plot. Before signing, the siblings complete mutation into all their names, agree the split of the landowners' flats among themselves in a separate family agreement, and require the developer to show plan approval before demolition. The agreement fixes completion dates, a monthly rent payable to the family during construction, and compensation for delay. These steps do not guarantee a smooth project, but they deal with the issues that most often derail one.
Planning and building control: the 2023 to 2026 changes
Two recent statutes affect real estate and construction in the division. The Sylhet Development Authority Act 2023 provides for a development authority for the Sylhet City Corporation area and adjoining areas notified by the Government. The official text records that the Act was brought into force by a statutory notification dated 19 January 2026.
The authority's functions include preparing and implementing a master plan; under section 18, no person, local authority or organisation may generally build infrastructure, roads or buildings or carry out a development project in its area without its clearance, and projects may not fill rivers, canals, beels or water bodies or obstruct their natural flow. A person wishing to use land for a purpose other than that shown in the master plan must apply in writing to the chairman, who decides within thirty days, with an appeal to the authority within sixty days of a refusal (section 15). Developers should check how the authority's clearance is being applied in practice alongside city corporation plan approval.
At the national level, the Bangladesh Building Regulatory Authority Act 2026, which replaced an ordinance of the same name, establishes an authority to act as regulator and supervisor of the bodies that approve building plans and enforce the building code, including development authorities, city corporations and municipalities (section 12). Outside those areas, the Government is to form building construction committees by gazette notification to approve plans (section 11). Building construction itself remains subject to the Building Construction Act 1952 and the rules and code made under building law.
Contractors, construction contracts and site safety
Whether the project is a tower or a village house, the construction contract is where risk is allocated. A good contract defines the scope by reference to approved drawings and specifications, fixes the price and payment stages against measurable milestones, sets a completion date with compensation for delay, deals with variations in writing, requires the contractor to comply with the building code and safety rules, provides for retention and defect correction, and sets out how disputes will be resolved, often by arbitration. Using sub-standard materials contrary to the agreement is a specific offence for developers under section 25 of the 2010 Act.
Construction sites employ large numbers of workers, many through labour contractors. The principal employer can be liable for wages a contractor fails to pay, and workplace safety duties apply; see labour act compliance. Building materials raise their own legal issues in Sylhet, where stone and sand extraction is restricted; see stone and sand quarrying.
Building from abroad
Diaspora families building a home in their village often rely on a relative to manage the contractor and payments. Written contracts, payments through bank accounts against stage certificates, photographs at each stage and an independent engineer's check are simple safeguards. Our insight on building a house in your village from abroad explains the permits and contracts.
Buying or investing in real estate and construction from abroad
For many diaspora families, buying a flat in Sylhet city or funding a family building is their most significant investment in Bangladesh. The risks are familiar: paying a developer who has not secured plan approval, buying into a project on land with an unresolved inheritance dispute, sending money to a relative's personal account, or signing an allotment letter that leaves out the protections the 2010 Act provides. A short set of checks reduces those risks considerably.
- Verify the developer's registration and the plan approval number shown in the prospectus.
- Check the land title, mutation and any joint venture agreement between the developer and the landowners.
- Read the allotment letter for handover dates, delay compensation, payment schedule, default consequences and specifications.
- Pay through bank transfers to the developer's account, as section 12 contemplates, and keep every receipt.
- Insist on registration of the sale deed within three months of full payment, as section 9 requires.
- If you cannot travel, give a limited power of attorney to a trusted person for specific steps, rather than a general one.
Remittances sent through banking channels also leave a documentary trail that helps with tax and, later, with any repatriation of sale proceeds. See remittance economy and diaspora investment in Sylhet for the wider picture of how real estate and construction investment from abroad is structured.
Disputes in real estate and construction
Disputes in the sector typically involve late handover, defects, unauthorised changes to plans, double allotment of flats, landowners refusing to hand over possession, developers abandoning projects and contractors claiming unpaid bills. Remedies include criminal complaints under the 2010 Act, civil suits for specific performance, refunds and damages, injunctions to stop construction or sales, consumer complaints and arbitration where the contract provides for it. The right route depends on the goal: a buyer who wants the flat needs a different strategy from one who wants a refund. See civil suits and injunctions.
Defects after handover
Defects such as leaks, cracks, faulty wiring or missing common facilities often appear months after handover. Allotment letters and construction contracts should include a defects liability period and a clear process for reporting and fixing defects, and flat owners should organise early, through an owners' association, to deal with common-area issues. Keep photographs and written complaints from the date a defect is discovered; delay weakens any claim. Where defects result from building outside the approved plan or using inferior materials, the 2010 Act's offences may also be relevant, alongside civil claims for repair costs or damages.
| Problem | Possible routes |
|---|---|
| Developer late in handing over | Refund with compensation under s.15; civil suit; complaint for offences where facts support it |
| Flat sold to someone else | Criminal complaint under s.24; injunction; suit for specific performance |
| Construction outside the approved plan | Complaint to the plan-approving authority; complaint under s.26 |
| Landowner refuses possession | Enforcement of the joint venture agreement; complaint under s.28 |
| Contractor defects or delay | Contractual claims; arbitration if agreed; retention |
How TRW & Co helps
We advise landowners, developers, contractors, buyers and diaspora investors across the real estate and construction sector in the Sylhet division: title checks, joint venture agreements and powers of attorney, developer registration and project approvals, allotment letters and sale deeds, construction contracts, and disputes before the courts and in arbitration. Clients abroad can instruct us by email at info@trw.co and receive documents for signature and authentication; local clients can meet us at our Sylhet office at Surma Tower, opposite the Judge Court. See sectors in the Sylhet economy, or contact us.
Frequently asked questions
Does a developer in Sylhet need to be registered?
Yes. Section 5 of the Real Estate Development and Management Act 2010 requires every developer to register with the relevant authority before carrying on real estate business in an area. Doing business without registration is an offence punishable with up to two years’ imprisonment, a fine of up to Tk 10 lakh, or both.
What can I do if my flat is not handed over on time?
Under section 15 of the 2010 Act, if the developer fails to hand over within the agreed time, it must refund all money paid with the agreed compensation within six months. If the contract fixes no rate, compensation is 15% of the money paid. You may also have civil remedies, and extensions agreed in writing affect the position.
Can a landowner cancel the power of attorney given to a developer?
A landowner who cancels a registered power of attorney given to a developer under a joint venture agreement without at least thirty days’ notice commits an offence under section 29 of the 2010 Act. Cancellation may still be justified where the developer is in serious breach, but take advice first.
Is the Sylhet Development Authority now in operation?
The Sylhet Development Authority Act 2023 has been brought into force by notification, according to the official text, and provides for an authority with master-planning and development clearance powers over the city corporation area and notified adjoining areas. How its clearance operates alongside city corporation approvals should be checked for each project.
I am building a house in my village from the UK. What should I insist on?
A written contract with drawings, a fixed price with stage payments, a completion date, and a requirement to follow the building code. Pay through bank accounts against stage certificates, get photographs at each stage and consider an independent engineer. Check whether plan approval is needed where the house is built.